NEW CONSTRUCTION
Center for Engineering & Technology
74,000 square feet
Will house programs in Engineering, Engineering Technology, Biomedical Equipment Repair Technology, Engineering Design Graphics, Electronics, and Computer Information Technology
Cosmetology Center
39,000 square feet
Will provide the latest in updated classrooms and state-of-the-art labs to enhance workforce training for those entering the cosmetology field.
Expansion of Building 23 (Fire House)
Size TBD
Will house the heating, air conditioning, and ventilation technology program
RENOVATIONS
Jones Building
53,000 square feet
Built in 1983
Repurpose and provide updated classrooms to house the early college high school programs for Clear Creek and Pasadena Independent School Districts.
Longenecker Building
93,000 square feet
Built in 1979
Repurpose and provide updated classrooms, internal spaces, and offices.
Bruce Building
57,325 square feet
Built in 1989
Renovate space that formerly housed student service personnel who relocated to the Welcome Center.
SITE / INFRASTRUCTURE
Study and upgrade security and access systems
Upgrade primary electrical service
Replace and relocate hot water and chilled water systems
Replace sanitary sewer
Demolish auto body building for new building site
Expand building automation system
Update data and technology infrastructure